Connect with us

WAPA

WAPA’s Commitment to Revitalizing Power Infrastructure in the St. Thomas-St. John District

Published

on

The Virgin Islands Water and Power Authority (WAPA) has acknowledged ongoing power disruptions in the St. Thomas-St. John district, attributing the issues to aging and damaged systems. These challenges have been particularly pronounced since September 2023, with the district experiencing frequent outages, including one that lasted nearly half a day.

The root of these disruptions traces back to excavation work in September, which necessitated week-long outage rotations to facilitate repairs. Weather-related incidents and underground system repairs further compounded the problem in the following months. A notable incident occurred at the Donald Francois substation in November, where infrastructure strain led to a significant failure. Ashley Byran, WAPA’s Chief Operating Officer of Electric, cited the lingering effects of the 2017 hurricanes on the electric distribution infrastructure, particularly impacting three major transmission lines and leading to repeated failures at the Donald Francois substation.

Ms. Byran explained that the current infrastructure was originally designed to allow two transmission lines to support the third. However, with only two lines operational, this setup proved insufficient to meet the district’s power demands, resulting in rotational outages.

In response, WAPA is actively pursuing solutions. The Federal Emergency Management Agency (FEMA) is expected to fund key mitigation projects, focusing on specific repairs and replacements. Ms. Byran detailed WAPA’s plans, including the emergency construction of an overhead composite pole transmission system and replacing damaged underground sections. These initiatives are anticipated to enhance service reliability and overall quality of life, addressing concerns such as the negative impact of power outages on tourism.

Looking ahead, WAPA anticipates beginning substantial foundational work in the coming months. Ms. Bryan emphasized the critical role of the Wärtsilä system, which, once fully operational, is expected to significantly reduce the likelihood of prolonged blackouts. Challenges in shipping have delayed the full commissioning of these state-of-the-art generators.

WAPA is committed to preventing future outages, developing new standard operating procedures for underground troubleshooting, and designing training programs for staff. These efforts aim to enhance their capability in identifying and addressing various faults, ultimately contributing to a more resilient and reliable power system for the St. Thomas-St. John district.

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

WAPA

Vitema Offices on St. Thomas Closed Due to WAPA Potable Water Disruption

Published

on

U.S. Virgin Islands – The Virgin Islands Territorial Emergency Management Agency (VITEMA) Director is advising the public that the St. Thomas offices are closed effective immediately due to a WAPA potable water disruption.

According to WAPA’s statement, the problem is expected to be fixed later this evening and, as such, VITEMA’s St. Thomas office will reopen as usual tomorrow, Wednesday, May 15, 2024 for normal operations, 8am-5pm.

The St. Thomas 911 operations remain functioning as usual.

 

Continue Reading

WAPA

Loud Boom at Randolph Harley Power Plant Leads to Safety Precautions

Published

on

A startling boom at the Randolph Harley Power Plant in St. Thomas prompted an evacuation of the V.I. Water and Power Authority (WAPA) personnel on Thursday. Contrary to initial fears of an explosion, the noise was identified as a safety feature activation—a rupture disk—intended to prevent damage to critical systems, according to WAPA spokesperson Shanell Petersen.

This safety mechanism, which triggered the evacuation, responds automatically when it detects potential threats to the plant’s integrity. The activation caused significant concern, initially described as an explosion by a WAPA official. In response, the V.I. Fire and Emergency Services dispatched teams, and the Virgin Islands Police Department secured the plant’s perimeter.

Petersen explained the evacuation was a necessary precaution due to the intensity of the noise. She clarified that such measures ensure the safety of the staff, highlighting that the rupture disk’s role is a proactive safety response.

The event occurs amid ongoing challenges for WAPA in maintaining consistent power in the St. Thomas-St. John District. Following a district-wide outage on Wednesday, the region experienced similar power interruptions again today. Petersen noted that the rupture disk incident does not directly relate to the generation of power but is a separate safety measure.

The power issues have had widespread repercussions. The V.I. Department of Education had to cancel classes in the district for the second consecutive day. “Due to the ongoing power outage affecting the St. Thomas-St. John District, all schools within the district will remain closed today, Thursday, May 9, 2024,” announced the Department. “We apologize for any inconvenience and ask the public to follow official updates for further information on school operations.”

Additionally, the V.I. Superior Court announced closures due to a water service interruption, and the V.I. Economic Development Authority reported disruptions to its telephone services.

In related community impacts, the Lockhart K-8 Music Department has postponed its Spring Concert scheduled for today due to the unstable power supply, affecting not only educational institutions but also community events across the island.

Continue Reading

WAPA

PSC Commissioner Calls for Hiring of Hearing Examiner Amid Concerns Over Water Safety in St. Croix

Published

on

During a recent meeting with representatives from the Water and Power Authority (WAPA), Public Services Commission (PSC) member David Hughes expressed significant concerns about the current state of water testing in St. Croix, following last year’s alarming discovery of elevated levels of lead and copper. Hughes pressed for immediate action, questioning the delay in hiring a hearing examiner—a role outlined on the PSC’s website as crucial for overseeing utility compliance with regulations.

Hughes emphasized that the role of the hearing examiner is to work closely with utilities to ensure they meet the commission’s standards, particularly in regular testing to safeguard public health. “The PSC should be actively ensuring that WAPA maintains a consistent testing program that we can trust on behalf of consumers,” he stated.

The dialogue grew tense when Hughes criticized the commission’s efforts, responding to PSC Executive Director Sandra Setorie’s assurances that progress was being made with, “We as a Commission are not fulfilling our obligations.” He pointed to WAPA’s reactive measures—conducting 65 water tests in response to complaints about water discoloration—as insufficient and indicative of a need for a robust, ongoing testing program.

WAPA’s Director of Water Distribution for St. Croix, Don Gregoire, defended their practices, stating that the water is tested daily in their own laboratory, following EPA guidelines which now mandate biannual testing. However, Hughes countered that without full transparency and understanding of the testing procedures, the commission could not confidently endorse the program.

The urgency for better oversight was further highlighted by a lawsuit alleging serious deficiencies at the St. Croix laboratory, including outdated certifications and improper sample collection. These revelations support Hughes’s argument for enhanced oversight to ensure WAPA’s accountability and transparency.

Hughes also pointed out a broader issue of information deficit and lack of transparency from WAPA, underscoring the PSC’s duty to keep the public informed. “We’re not doing our job in regulatory oversight,” he lamented.

In a positive note, WAPA Chief Operating Officer for Water, Noel Hodge, announced a substantial FEMA grant aimed at overhauling St. Croix’s water infrastructure over the next two decades, with a detailed capital improvement plan underway and initial construction expected to start within three years.

Hughes’s call for the appointment of a hearing examiner underscores a critical need for PSC to enhance its regulatory role and ensure that such public health emergencies do not recur, reflecting a commitment to uphold safety and transparency in public utilities.

Continue Reading

Trending