WAPA
Swift Recovery: WAPA Achieves Full Power Restoration in St. Thomas and St. John Following Crucial Repairs
The Virgin Islands Water and Power Authority (WAPA) triumphantly declared the full restoration of electrical services to all feeders in St. Thomas and St. John late this Saturday, following a series of power disruptions and scheduled outages that plagued the islands.
This restoration is a beacon of success after the unfortunate incident on September 16, where construction activities accidentally breached a duct bank, a crucial component designed to shield utility lines and cables. This breach resulted in significant damage to the internal electrical cable, directly affecting the pivotal Feeder 13. This feeder is integral in channeling power from the Randolph Harley Power Plant (RHPP) located in St. Thomas to the Tutu Substation.
Feeder 13, in conjunction with Feeder 12, serves as the primary arteries for transmitting the power generated at RHPP. The impairment to Feeder 13 imposed an additional burden on Feeder 12, compelling it to bear the majority of the electrical load for the St. Thomas/St. John District.
WAPA extended its heartfelt appreciation to the local community for their enduring patience throughout this demanding time and lauded its workforce for their unwavering dedication and relentless efforts to restore power. The authority highlighted the steadfast commitment of its team and the essential cooperation of Electrical Conductors LLC and Haugland VI as pivotal to the successful restoration endeavor. Both firms deployed additional personnel to expedite the repair process.
The restoration of power is not just a technical achievement but also a testament to the resilience and collaborative spirit of the community and the involved organizations. The swift and efficient response ensured minimal disruption to the residents of St. Thomas and St. John, allowing them to resume their normal lives with the assurance of a stable power supply.
This incident has underscored the importance of robust infrastructure and the need for meticulous attention during construction activities to prevent any inadvertent damage to critical utility components. It also highlighted the significance of community support and the value of dedicated personnel in overcoming challenges and ensuring the continuity of essential services.
In conclusion, the successful restoration of power to St. Thomas and St. John by WAPA, with the support of Electrical Conductors LLC and Haugland VI, is a shining example of resilience, cooperation, and commitment to service, reflecting the strength and unity of the Virgin Islands community.
WAPA
Restoration Achieved: WAPA Unit 23 Back Online, Rotational Outages End in STT/STJ
The Virgin Islands Water & Power Authority (WAPA) announced late Wednesday that Unit 23, which had been out of service and causing rotational outages across the St. Thomas and St. John (STT/STJ) district, is now operational following successful repairs. This development has brought an end to the recent schedule of rotational outages in the area.
The restoration of Unit 23 was made possible by the dedicated efforts of WAPA’s plant personnel, who managed to install a replacement transducer, thereby restoring the unit to full functionality. This repair marks a significant step towards stabilizing the power supply for residents and businesses that have been adversely affected by the outages.
WAPA expressed gratitude to the community for their patience during this challenging period, acknowledging the hardships and inconveniences caused by the power interruptions. The authority highlighted that their team, made up of local community members who were also impacted by the outages, worked with diligence and urgency to ensure the repairs were carried out safely and efficiently.
“We want to emphasize that the WAPA team is comprised of community members who were also impacted by these outages,” the statement read. “This process was not taken lightly, and we worked with great urgency while also safely conducting repairs.”
This announcement follows WAPA’s recent successful repairs to Feeder 13, which resolved issues stemming from a damaged underground cable.
WAPA
WAPA Completes Feeder 13 Repairs; Rotational Outages Persist Due to Offline Unit 23
The V.I. Water and Power Authority (WAPA) has successfully repaired Feeder 13, resolving issues from a damaged underground cable. This extensive repair effort, completed last Friday evening, has brought relief to numerous customers in the St. Thomas-St. John district.
Despite this progress, challenges remain as Unit 23 is still offline, necessitating ongoing rotational power outages. These outages affect various feeders, contributing to the region’s power instability.
The Feeder 13 repair involved WAPA’s line department, transmission, and distribution teams, along with contractors Haugland VI and F&R Electric. They conducted a meticulous inspection and testing of the approximately five-mile-long cable, including a two-mile underground segment with 29 manholes. This process was essential to pinpoint the fault location and execute necessary repairs, according to a WAPA release.
The repair process faced challenges, particularly heavy rainfall last week, which required pumping water from manholes and prolonged the preparatory phase. WAPA utilized a fault indicator system to narrow down potential causes and streamline the repair process.
“We sincerely understand the major inconvenience this situation caused and assure you that crews were committed to quickly and safely restoring power,” stated WAPA.
Concurrently, WAPA faced additional challenges as Unit 23 at the power plant went offline last week for testing, leading to unexpected rotational outages. Customers on Feeders 6A and 7A experienced intermittent two-hour service interruptions due to the reduced generation capacity.
As of Monday, WAPA reported that the Wartsila Phase 1 Unit 3 has completed regular maintenance and is back online, helping to alleviate the generation shortfall. However, an updated rotational outage schedule remains in effect for the St. Thomas-St. John district until Unit 23 is fully operational again. WAPA plant personnel are exploring two potential solutions to expedite the return of Unit 23, including acquiring a new Megawatt transducer.
WAPA
PFA Selects Ernst & Young for WAPA Turnaround Management
The Public Finance Authority (PFA) has appointed Ernst & Young (E&Y) to manage the turnaround of the Water and Power Authority (WAPA). This decision emerged from an emergency PFA meeting on Wednesday, where the board unanimously agreed to E&Y’s proposal following an executive session reviewing four bids.
Lorelei Farrington, PFA’s staff counsel, detailed that an evaluation committee comprising PFA and WAPA representatives had meticulously reviewed the proposals earlier this year. The most expensive bid was discarded due to its significantly higher cost. The remaining proposals were assessed on project understanding, approach appropriateness, project plan effectiveness, and overall value.
“Based on the results of that evaluation, the committee recommends that a contract for the turnaround management services be awarded to Ernst & Young,” said Ms. Farrington. She highlighted E&Y’s extensive experience in addressing financial and operational distress and their broad capabilities in restructuring and turnaround practices.
E&Y’s existing relationship with WAPA positions them uniquely to provide further insights into the turnaround process. At an estimated cost of $450,000, E&Y’s proposal was the most economical among the bids, which ranged from $450,000 to $9 million.
The turnaround project is structured into three phases:
- Phase One: An initial assessment of WAPA to be completed within 120 days, resulting in a report for the legislature and governor on the authority’s financial status. This phase includes data collection on WAPA’s programs and projects, energy plans, debt consolidation, water quality, and service improvement plans.
- Phase Two: A 60-day period to submit a report detailing short-term measures to reduce the LEAC, recommendations for base rate reductions over 24 months, and strategies for incorporating renewable energy and reducing fossil fuel dependency over five years. It also involves organizational restructuring, debt management, and ensuring reliable water quality standards.
- Phase Three: Implementation assistance for all recommendations from phase two.
Board member Dorothy Isaacs expressed skepticism about spending more funds on WAPA without guaranteed improvements but ultimately supported the contract as a “final last-ditch effort” to resolve ongoing issues. The board approved a contract extension to E&Y, not exceeding $500,000.
PFA board chair Governor Albert Bryan Jr. noted that legislative mandates necessitated this move. Despite initially vetoing the legislation, which was later overridden, Governor Bryan now views this initiative as a positive step. “In retrospect, I think it will be a valuable tool,” he stated, acknowledging the complexity and unknown challenges within WAPA that the report aims to clarify.
The governor also appreciated the legislature for pushing this directive, despite it being an unfunded mandate from the 35th Legislature.
-
Education10 months ago
Education Board Seeks Input on Schools Through Comprehensive Survey
-
Education1 year ago
CTE Board Enthusiastic About New Curriculum Standards, Yet Anxious Over Apprenticeship Support
-
Crime1 year ago
Registered Sex Offender Detained for Illegal Firearm Possession During Annual Surveillance Drive
-
Development8 months ago
Costs Surge as Donoe Estates Housing Project Resumes with New Contractor
-
Crime1 year ago
St. John’s Westin Resort Scene of Armed Robbery, Prompting Heightened Police Vigilance
-
Videos2 years ago
2022 Gubernatorial Election: Voters Speak Out
-
Videos2 years ago
Gubernatorial Teams Celebrate St. Croix’s Bull & Bread Day
-
Crime1 year ago
Unraveling the Home Invasion in St. John: Suspect Held on $100,000 Bail