The Virgin Islands Water and Power Authority’s governing board approved several contract and administrative items at its Sept. 28 meeting.

Under Planning and Economic Development Committee matters, the board approved a 12-month no-cost time extension and amended payment schedule for the Hannah’s Rest Rehabilitation Project, identified as SC-02-23. It also approved a $2,690,932.24 change-order increase and time extension for the Campo Rico Waterline Rehabilitation Project, SC-02-213, setting an end date of April 28, 2025. The board also authorized WAPA to award the Northside Road Waterline Rehabilitation Design contract to Stanley Consultants for $6.45 million.

Under Finance and Audit Committee matters, the board approved an amendment to the Composite Pole Project contract, SC-20-21, with Haugland Energy for $7,783,100.61 for additional work in St. Thomas, along with a time extension through July 31, 2024. The board also approved renewal of the 2024 employee benefits package.

The release also said Lionel Selwood had joined the governing board.

On a communication matter, the release said Chairman Fleming, Member Turnbull and Member Boynes-Jackson voted yes, while Member Selwood and Secretary Young abstained. The motion passed, 3-0, with two abstentions.